Peugeot405
1. The maintenance instruction
2. Maintenance service
3. Engines
    3.1. Petrol engines
    3.2. Diesel engines
    3.3. The petrol engine 1,4 дм3
      3.3.1. A technical characteristics
      3.3.2. Check and adjustment of a backlash of valves
      3.3.3. Check and adjustment of a corner of an advancing of ignition
      3.3.4. Carburettor adjustment
      3.3.5. Removal of the air filter
      3.3.6. Removal of a head of the block of cylinders
      3.3.7. Installation of a head of the block of cylinders
      3.3.8. Removal and installation of the power unit from the petrol engine 1,4 дм3
      3.3.9. Features of dismantling of the petrol engine 1,4 дм3
      3.3.10. Engine TU3 dismantling
      3.3.11. Dismantling of a head of the block of cylinders
      3.3.12. Assemblage of a head of the block of cylinders
      3.3.13. Definition of the size of loose leaves
      3.3.14. Engine TU3 assemblage
      3.3.15. Removal of the oil pump
      3.3.16. Dismantling of the oil pump
      3.3.17. Removal of the pump of a cooling liquid
      3.3.18. Service and repair of a transmission of type МА
      3.3.19. Removal and installation of a transmission of type МА
      3.3.20. Transmission dismantling
      3.3.21. Dismantling of a secondary shaft
      3.3.22. Dismantling of a primary shaft
      3.3.23. Differential dismantling
      3.3.24. Dismantling of knot of plugs with their axes
      3.3.25. Dismantling of the plug of synchronizers
      3.3.26. Verification of parts of a transmission
      3.3.27. Assemblage of the plug of synchronizers
      3.3.28. Assemblage of knot of plugs with their axes
      3.3.29. Differential assemblage
      3.3.30. Assemblage of a primary shaft
      3.3.31. Assemblage of a secondary shaft
      3.3.32. Transmission assemblage
    3.4. Ignition system
4. Fuel system
5. Systems of greasing, cooling
6. Release system
7. Coupling
8. Transmissions
9. Power shafts
10. A steering
11. Suspension brackets
12. Brake system
13. A body
14. An electric equipment


3.3.3. Check and adjustment of a corner of an advancing of ignition
THE GENERAL DATA

Ignition system

Drawing above – the basic scheme,
Drawing below – the scheme of connections,
1 – the accumulator,
2 – the coil of ignition,
3 – the module of strengthening,
4 – the ignition distributor

Signs for ignition installation on a flywheel

The corner of an advancing of ignition is checked idling after removal from the distributor of ignition of the vacuum pipeline and closing of the pipeline by a stopper. Signs for check of installation of ignition are visible through an aperture in картере couplings (a plate with divisions and a sign on a flywheel). The engine should be heated-up to temperature of normal work.

PERFORMANCE ORDER
1. To connect a stroboscopic lamp to a wire of a high voltage of 1st cylinder according to the instruction of the manufacturer of a lamp.
2. To remove from a vacuum regulator of the distributor of ignition the vacuum pipeline and to close the pipeline a stopper.
3. To start the engine and to check up turns of idling which should be equal 750 rpm.
4. To shine with a stroboscopic lamp control signs in an aperture картера couplings and to read the instrument of size of an advancing of ignition.
5. If this value differs from 8 ° (at 750 rpm of the engine), it is necessary to weaken fastening of the distributor of ignition and to turn it so that a sign on a flywheel was combined with division 8 ° on a plate.
6. To tighten the distributor of ignition and repeatedly to check up a corner of an advancing of ignition by means of a stroboscopic lamp.